Project Duration

18 days

Critical Paths

  • F → H → A
  • F → J → A

Select Task by Key

Selected Task

Click on a task to view its details

PERT Chart

Customize the appearance using the sidebar

Start0000C0268F0808G0358E28915H813813J813813K8101113A13181318B13171418D13161518Finish18181818